Next week is the milestone week for 4.18 M3.


Monday: Last day of development (and even then, no "big changes").

After Monday 18:00 ET, no feature work or unrelated fixes are allowed --
only regression fixes.



Tuesday: All-day test pass. Nobody should develop or fix anything.
Literally spend the entire day testing.



Wednesday: Fix day with a focus on fixing regressions found during the test
day (Tuesday). No unrelated fixes. Review and thoroughly test all commits.

- The last Wednesday build is the release candidate every team signs off on
Thursday.

- The "New and Noteworthy" entries are due on Wednesday evening:

Git repo: ssh://git.eclipse.org/gitroot/www.eclipse.org/eclipse/news.git

Gerrit: ssh://git.eclipse.org:29418/www.eclipse.org/eclipse/news.git

Live website: https://www.eclipse.org/eclipse/news/4.18/



Thursday: Sign-off after re-testing, or at least confirming no changes have
been made to your component's code since the last time the component was
tested well.



Friday: Build is officially declared and made available.

- The master branch stays closed until the milestone is officially
released. (That is, it is not enough that your component has signed off.)


Regards,


-- 
Alexander Kurtakov
Red Hat Eclipse Team
_______________________________________________
platform-dev mailing list
platform-dev@eclipse.org
To unsubscribe from this list, visit 
https://www.eclipse.org/mailman/listinfo/platform-dev

Reply via email to