Spring 2010 Outage (U-1) Goal = 30 Actual =42 PCEs Outage duration 55 days Level 1 = 32 Level 2 = 10 Level 3 = 0
Fall 2010 Outage (U-3) Goal = 30 Actual 22 PCEs Outage duration 35 days Level 1 = 20 Level 2 = 2 Level 3 = 0 Spring 2009 Outage (U-3) Goal = 40 Actual = 36 PCEs Outage duration 44 days Level 1 = 29 Level 2 = 7 Level 3 = 0 Fall 2009 Outage (U-2) PCEs Goal = 40 Actual = 28 Outage duration 59 days Level 1 = 21 Level 2 = 7 Level 3 = 0 -----Original Message----- From: [email protected] [mailto:[email protected]] On Behalf Of [email protected] Sent: Monday, November 29, 2010 7:04 AM To: [email protected] Subject: Powernet: Outage PCE's Looking for PCE data for outages. How many Outage PCEs did you have? What was the outage goal? What EPRI level were the PCEs? What was the outage duration in days? What year? Thanks. June L. Scott [email protected] Phone: 419-321-8555 Cell: 419-367-6651 Davis Besse Nuclear Power Station 5501 N State Route 2 Oak Harbor, Oh 43449 ----------------------------------------- The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify us immediately, and delete the original message. ----------------------------------- Powernet - a service of the Health Physics Society Power Reactor Section Powernet archives at http://www.mail-archive.com/[email protected]/ Reply to: [email protected] If Questions, contact Mike Russell, CHP at [email protected] Email Firewall made the following annotations --------------------------------------------------------------------- --- NOTICE --- This message is for the designated recipient only and may contain confidential, privileged or proprietary information. If you have received it in error, please notify the sender immediately and delete the original and any copy or printout. Unintended recipients are prohibited from making any other use of this e-mail. Although we have taken reasonable precautions to ensure no viruses are present in this e-mail, we accept no liability for any loss or damage arising from the use of this e-mail or attachments, or for any delay or errors or omissions in the contents which result from e-mail transmission. --------------------------------------------------------------------- ----------------------------------- Powernet - a service of the Health Physics Society Power Reactor Section Powernet archives at http://www.mail-archive.com/[email protected]/ Reply to: [email protected] If Questions, contact Mike Russell, CHP at [email protected]