Spring 2010 Outage (U-1)                Goal = 30       Actual =42 PCEs 
Outage duration 55 days
Level 1 = 32            Level 2 = 10            Level 3 = 0 


Fall 2010 Outage (U-3)          Goal = 30       Actual  22 PCEs 
Outage duration 35 days
Level 1 = 20            Level 2 = 2             Level 3 = 0 


Spring 2009 Outage (U-3)                Goal = 40       Actual = 36 PCEs 
Outage duration 44 days
Level 1 = 29            Level 2 = 7             Level 3 = 0 


Fall 2009 Outage (U-2) PCEs     Goal = 40       Actual = 28
Outage duration 59 days
Level 1 = 21            Level 2 = 7             Level 3 = 0 


-----Original Message-----
From: [email protected] [mailto:[email protected]] On Behalf Of 
[email protected]
Sent: Monday, November 29, 2010 7:04 AM
To: [email protected]
Subject: Powernet: Outage PCE's


Looking for PCE data for outages.

How many Outage PCEs did you have?
What was the outage goal?
What EPRI level were the PCEs?
What was the outage duration in days?  What year?

Thanks.

June L. Scott
[email protected]
Phone: 419-321-8555
Cell:      419-367-6651
Davis Besse Nuclear Power Station
5501 N State Route 2
Oak Harbor, Oh 43449


-----------------------------------------
The information contained in this message is intended only for the
personal and confidential use of the recipient(s) named above. If
the reader of this message is not the intended recipient or an
agent responsible for delivering it to the intended recipient, you
are hereby notified that you have received this document in error
and that any review, dissemination, distribution, or copying of
this message is strictly prohibited. If you have received this
communication in error, please notify us immediately, and delete
the original message.
-----------------------------------
Powernet - a service of the Health Physics Society Power Reactor Section

Powernet archives at http://www.mail-archive.com/[email protected]/

Reply to: [email protected]
If Questions, contact Mike Russell, CHP at [email protected]

Email Firewall made the following annotations

---------------------------------------------------------------------
--- NOTICE ---

This message is for the designated recipient only and may contain confidential, 
privileged or proprietary information.  If you have received it in error, 
please notify the sender immediately and delete the original and any copy or 
printout.  Unintended recipients are prohibited from making any other use of 
this e-mail.  Although we have taken reasonable precautions to ensure no 
viruses are present in this e-mail, we accept no liability for any loss or 
damage arising from the use of this e-mail or attachments, or for any delay or 
errors or omissions in the contents which result from e-mail transmission.

---------------------------------------------------------------------

-----------------------------------
Powernet - a service of the Health Physics Society Power Reactor Section

Powernet archives at http://www.mail-archive.com/[email protected]/

Reply to: [email protected]
If Questions, contact Mike Russell, CHP at [email protected]

Reply via email to