DC Cook does the following.

Does your site use:

DL?
DA?
MDA?
CL?
LD?
LC?
LLD?
MDC?
ABC?
123?

DC Cook uses MDA for Alpha and Beta counters.  Specifically the Ludlum
3030P and the Canberra S5E.  Also, procedurally we assume the LLD is the
same as the MDA.

What are your technicians expected to calculate?

Since the Ludlum 3030P and the Canberra S5E calculate the MDA through
internal firmware, the technicians are not required to calculate anything.

How do you define these mathematically – what formulas do you use for
each?

If you need the individual formulas that the instruments calculate, just
let me know and I can provide you with them.

What is your basis – that is, what is the regulation you point to for your
basis?

EPRI document 1013509 is used for alpha guidance.
The Pland ODCM is used for LLD calculation.

Annie Sekel
Health Physicist-Assoc
D.C Cook Nuclear Plant
[email protected]
Phone: 269-465-5901 x2088
Pager: 269-708-1020






"Pell, Bryan" <[email protected]>
Sent by: [email protected]
05/23/2011 04:16 PM
Please respond to
[email protected]


To
"'[email protected]'" <[email protected]>
cc

Subject
Powernet: MDC vs. Critical Level






Constellation needs help with its technical basis for counting statistics.

Does your site use:

DL?
DA?
MDA?
CL?
LD?
LC?
LLD?
MDC?
ABC?
123?

What are your technicians expected to calculate?

How do you define these mathematically – what formulas do you use for
each?
What is your basis – that is, what is the regulation you point to for your
basis?

Thanks for your support,

Bryan

Bryan S. Pell
R.E. Ginna Nuclear Power Plant
Senior Plant Health Physicist
(585) 771-3804
[email protected]
P Please consider the environment before printing


>>> This e-mail and any attachments are confidential, may contain legal,
professional or other privileged information, and are intended solely for
the
addressee.  If you are not the intended recipient, do not use the
information
in this e-mail in any way, delete this e-mail and notify the sender.
CEG-IP2



----------------------------------------------------------------
This e-mail message and all attachments transmitted with it from the
Nuclear Generation Group of American Electric Power are for the sole
use of the intended recipient(s) and may contain confidential and
privileged information.  Any unauthorized review, use, disclosure or
distribution is prohibited.  If you are not the intended recipient, please
contact the sender by reply e-mail and destroy all copies of the original
message.

Reply via email to