Palo Verde requests information on the following: 

 

Palo Verde is currently planning upgrades to our remote monitoring
capabilities.  Presently, most of our efforts have been limited
installations that are essentially "temporary" that is not considered a
permanent plant modification.  This is especially true for our efforts
done in Containment Buildings during refueling outages where all
equipment is brought in and then removed.  Our "temporary" installations
consist primarily of monitoring of filters and liquid radwaste tanks and
components.

 

With that in mind, Palo Verde would like to know:

 

1.      Have you installed any permanent infrastructure, e.g., fiber
optics, coaxial cable, communications systems, etc., used to support
remote monitoring efforts at your station? 

Yes

 

If yes, could you provide some additional information such as:

 

*         What buildings (e.g., Containment, Fuel, Auxiliary, Radwaste)
if any have you installed permanent infrastructure to support remote
monitoring equipment.

Reactor Building            12 original, 36 more ran 2009

Drywell                          12 to each DW cabinet, none permanently
installed inside.

Refuel Floor                   12 original, 36 more ran 2009

Rad Waste                    12 ran 2010

Turbine Building             36 ran in 2009

 

A brief description such as: Aux Bldg, fiber run, limited access to
certain rooms, etc. will suffice. 

 

*         What was your cost range for all installations e.g., 10 to 20
million, it doesn't have to be too specific.

$150k T&M, no mods, done using Fee-air procedure, purchased fiber, LOE
for EM to run

 

2.      If no, do you have any plans to install permanent infrastructure
to support remote monitoring in the future?

 

 

Thanks, Seth.

 

**********************************************************************
Seth J. Kanter, CHP, RRPT
Sr. Health Physicist
Palo Verde Nuclear Generating Station
Mail Sta. 7397
5801 S. Wintersburg Rd.
Tonopah, AZ 85354
Phone (623) 393-3130
Fax (623) 393-1853
Unless otherwise noted, all opinions are my own 
Liviu Librescu 
********************************************************************** 

 

 

 

 

 

--- NOTICE ---

This message is for the designated recipient only and may contain
confidential, privileged or proprietary information.  If you have
received it in error, please notify the sender immediately and delete
the original and any copy or printout.  Unintended recipients are
prohibited from making any other use of this e-mail.  Although we have
taken reasonable precautions to ensure no viruses are present in this
e-mail, we accept no liability for any loss or damage arising from the
use of this e-mail or attachments, or for any delay or errors or
omissions in the contents which result from e-mail transmission.




-----------------------------------------
**************************************************
This e-mail and any of its attachments may contain Exelon
Corporation proprietary information, which is privileged,
confidential, or subject to copyright belonging to the Exelon
Corporation family of Companies. 
This e-mail is intended solely for the use of the individual or
entity to which it is addressed.  If you are not the intended
recipient of this e-mail, you are hereby notified that any
dissemination, distribution, copying, or action taken in relation
to the contents of and attachments to this e-mail is strictly
prohibited and may be unlawful.  If you have received this e-mail
in error, please notify the sender immediately and permanently
delete the original and any copy of this e-mail and any printout.
Thank You.
**************************************************

Reply via email to