Note: This is a jobs stimulus program!

Fukushima decommissioning will take at least three decades
October 29, 2011 
Asahi Shimbum

A draft road map outlining the more than 30-year process of decommissioning and 
dismantling the crippled reactors at the Fukushima No. 1 nuclear power plant 
was published by the Japan Atomic Energy Commission (AEC) on Oct. 28.
The extraction of fuel rods in the storage pools at the reactors will begin 
around 2014, according to the plan, and removal of melted fuel rods within the 
reactors is expected to start around 2021.
The whole decommissioning process could be finished by 2041, but the authors of 
the draft report warn that significant delays are possible because they have 
not had access to full details of the extent of damage to the nuclear reactors 
and fuel rods.

Tokyo Electric Power Co. (TEPCO), the plant operator, will draw up detailed 
plans on the basis of the final report, due to be finalized by the end of the 
year, and will set about the decommissioning process as soon as a "cold 
shutdown" of the reactors is achieved, officials said. A cold shutdown is a 
state in which a nuclear reactor is kept at low temperature on a sustained 
basis.

A total of 1,496 fuel rods are held in the damaged No. 1, No. 2, No. 3 and No. 
4 reactors, and a further 3,108 fuel rods are stored in the spent fuel storage 
pools at those four reactors. Melted fuel rods are thought to have fallen to 
the bottom of the pressure vessels causing some leakage into containment 
vessels at the No. 1 through No. 3 reactors, which were operating when the 
tsunami hit the plant on March 11.

The decommissioning process at the Three Mile Island nuclear power plant in the 
United States, where a core meltdown occurred in 1979, was a key reference 
point for report's authors.

The draft says decommissioning at Fukushima will begin with decontamination of 
the interiors of the reactor buildings, repairs to the damaged containment 
vessels, and refilling containment vessels with water.
Equipment to remove melted fuel rods will be inserted into the reactors and 
extraction will start around 2021. The extraction of fuel from the interior of 
the reactors is expected to be completed around 2026, although the report does 
not give a precise date.

The cranes that would normally be used to extract spent fuel rods were broken 
by the hydrogen explosions that ripped through the No. 1, No. 3 and No. 4 
reactor buildings following the tsunami. New cranes will be installed to 
replace them, and the extraction of fuel from the spent fuel storage pools is 
expected to begin around 2014.

The draft report says that the government, research institutions, TEPCO and 
manufacturers will set up a research and development headquarters and work 
closely with overseas bodies.

"We envision that the extraction of fuel rods will be completed in about five 
years," said Hajimu Yamana, professor at the Kyoto University Research Reactor 
Institute who led the committee that drew up the draft report. "We hope to 
complete the decommissioning process in about the same time that it usually 
takes to decommission typical nuclear reactors, but we may need longer."

-----------------------------------
Sander C. Perle 
President
Mirion Technologies
Dosimetry Services Division 
2652 McGaw Avenue
Irvine, CA 92614
 
+1 (949) 296-2306 (Office)
+1 (949) 296-1130 (Fax)
 
Mirion Technologies: http://www.mirion.com/
"Protecting people, property and the environment"


-----------------------------------
Powernet - a service of the Health Physics Society Power Reactor Section

Powernet archives at http://www.mail-archive.com/[email protected]/

Reply to: [email protected]
If Questions, contact Mike Russell, CHP at [email protected]

Reply via email to