WASHINGTON - Federal regulators have approved a nuclear reactor designed by 
Westinghouse Electric that could power the first nuclear plants built from 
scratch in this country in more than three decades.

The Nuclear Regulatory Commission unanimously approved the AP1000 reactor 
Thursday. The certification, effective immediately, will be valid for 15 years.



NRC Chairman Gregory Jaczko said the newly approved design would ensure safety 
through simplified, passive security functions and other features. He said 
plants using the design could withstand damage from an airplane crash without 
significant release of radioactive materials - an issue that gained attention 
after the 2001 terrorist attacks.



Approval of the design is a major step forward for utility companies in 
Georgia, Florida and the Carolinas that have billions of dollars riding on 
plans to build AP1000 reactors in the Southeast. Without NRC approval, the 
utilities could not have gotten a license to build their plants.

Regulators approve nuclear reactor design they say is safe

Federal officials approved an earlier version of the AP1000 reactor in 2006, 
but it was never built in the United States. Four AP1000 reactors are now under 
construction in China.

Aris Candris, Westinghouse president and CEO, said the road to receiving design 
certification of the AP1000 "has been long and sometimes arduous."



The NRC vote brings the U.S "one step closer to constructing AP1000 units and 
putting thousands to work to ultimately provide future generations with safe, 
clean and reliable electricity," he said.

Utilities in Georgia and South Carolina have been waiting for the design 
certification so they can move ahead with applications to build two reactors in 
each state.



Atlanta-based Southern Co. applied to build the first two AP1000 reactors at 
Plant Vogtle near Augusta, Ga. The $14 billion effort is the pilot project for 
the new reactor and a major test of whether the industry can build nuclear 
plants without the delays and cost overruns that plagued building years ago. 
President Barack Obama's administration has offered the project $8 billion in 
federal loan guarantees as part of its pledge to expand nuclear power.

Close on its heels is SCANA Corp., which is also seeking permission to build 
two reactors at an existing site in Jenkinsville, S.C.



Other applications that use the AP1000 design include two plants in Florida, 
one and South Carolina and another in North Carolina. Each application is for 
two reactors.



Even with the design certification, it remains unclear when the Vogtle reactors 
will receive final approval - a major concern for Southern Co. since any delays 
could increase the cost of the project.



The biggest difference between the AP1000 and existing reactors is in the 
safety systems, including a massive water tank on top of its cylindrical 
concrete-and-steel shielding building. In case of an accident, water would flow 
down and cool the steel container that holds critical parts of the reactor - 
including its hot, radioactive nuclear fuel.



An NRC taskforce examining the nuclear crisis in Japan said licensing for the 
AP1000 should go forward because it would be better equipped to deal with a 
prolonged loss of power - the problem that doomed the Fukushima Dai-ichi plant.

Marilyn Kray, president of NuStart Energy Development, a nuclear industry 
consortium that has worked to demonstrate the design's effectiveness, said she 
was pleased to see the design move forward.

"The AP1000 is the reactor design that will set the foundation for the next 
generation of nuclear plants in the U.S.," Kray said.



A nuclear watchdog group called the vote disappointing, saying the NRC should 
have done a new analysis in the wake of the Japan crisis, which occurred after 
a March 11 tsunami sent three reactors at the Fukushima Dai-ichi plant into 
meltdowns in the worst nuclear crisis since Chernobyl in 1986.



A new study could have helped identify and correct any vulnerabilities based on 
lessons learned from Fukushima, said Edwin Lyman, a senior scientist at the 
Union of Concerned Scientists.

"It would be more efficient and cost-effective to address problems that could 
be corrected at the design stage now, before any new plants are constructed," 
Lyman said.



After plants are built, any new safety requirements would have to be addressed 
through costly retrofits and other actions, Lyman said, adding that he was "far 
from convinced" that the AP1000's passive safety features would be effective in 
coping with severe accidents.



Under existing rules, a reactor design that commissioners have voted to approve 
must be published in the Federal Register for 30 days before it is legally 
effective. Southern Co. officials asked the NRC to make the design effective 
immediately after the vote, a request that was granted. Publication in the 
Federal Register is expected by Jan. 5.

-----------------------------------
Sander C. Perle
President
Mirion Technologies
Dosimetry Services Division
2652 McGaw Avenue
Irvine, CA 92614

+1 (949) 296-2306 (Office)
+1 (949) 296-1130 (Fax)

Mirion Technologies: http://www.mirion.com/
"Protecting people, property and the environment"

Reply via email to