At STP our seal table is in a room and controlled as a LHRA. We control the in-core manipulations with a danger tag (owned by HP) on the power supply to the cabinet in the control room.
When we do flux mapping we control the entire RCB as a LHRA due to the dose rates outside the room. Normally our RCB is posted as a Radiation Area with all the LHRA/HRA independently controlled. Thanks Roger ________________________________ From: [email protected] [mailto:[email protected]] On Behalf Of Barber, Jerry Sent: Friday, January 20, 2012 9:42 AM To: '[email protected]' Subject: Powernet: Incore System Controls During Refuel Outages Robinson has the following question for other PWRs: How do you ensure that Incore detectors are not inadvertently operated during refueling outages while personnel are present in containment? Is a clearance routinely taken out on your Incore System at the beginning of a refueling outage? Do you normally keep your seal table room locked during refuel outages?