At STP our seal table is in a room and controlled as a LHRA. We control the 
in-core manipulations with a danger tag (owned by HP) on the power supply to 
the cabinet in the control room.

When we do flux mapping we control the entire RCB as a LHRA due to the dose 
rates outside the room.

Normally our RCB is posted as a Radiation Area with all the LHRA/HRA 
independently controlled.

Thanks Roger

________________________________
From: [email protected] [mailto:[email protected]] On Behalf Of 
Barber, Jerry
Sent: Friday, January 20, 2012 9:42 AM
To: '[email protected]'
Subject: Powernet: Incore System Controls During Refuel Outages

Robinson has the following question for other PWRs:

How do you ensure that Incore detectors are not inadvertently operated during 
refueling outages while personnel are present in containment?

Is a clearance routinely taken out on your  Incore System at the beginning of a 
refueling outage?

Do you normally keep your seal table room locked during refuel outages?