Dresden is in the process of changing the current station scheduling
database from Project View (PV) to P6. As PV is an Oracle database, we
have been successful using the data in PV via ODBC connections to import
data into an MS Access database, and using the durations, resources,
etc. to calculate estimates for the work activities. As I understand it,
P6 does not allow ODBC connections. Not having much other info about P6
at this time, we are uncertain what the ramifications on our estimating
process is going to be. If the data is available via Excel, or some
other spreadsheet, at least it could be imported and manipulated, even
if it is adding an extra step.

 

My question is does anybody else have any experience with P6, as far as
importing data from the station schedule to use in the exposure
estimating process?

 

Any help, contact info, etc. would be appreciated.

 

Joel Estes

Dresden ALARA

815-416-2710

 




-----------------------------------------
**************************************************
This e-mail and any of its attachments may contain Exelon
Corporation proprietary information, which is privileged,
confidential, or subject to copyright belonging to the Exelon
Corporation family of Companies. 
This e-mail is intended solely for the use of the individual or
entity to which it is addressed.  If you are not the intended
recipient of this e-mail, you are hereby notified that any
dissemination, distribution, copying, or action taken in relation
to the contents of and attachments to this e-mail is strictly
prohibited and may be unlawful.  If you have received this e-mail
in error, please notify the sender immediately and permanently
delete the original and any copy of this e-mail and any printout.
Thank You.
**************************************************

Reply via email to