Hi All,

Do you have a formalized process for suspending Emergency Responder 
qualifications due to RP issues.  For example:

1) Do you allow declared pregnant workers (DPW) to fill control room minimum 
staff shift positions?  If not, do you have a formalized process for suspending 
a qualification or is the process tracking manually.

2) Do you allow DPWs to fill RP/Chemistry Technician minimum staffing shift 
positions?  Again, if not, do you have a formalized process.

Diablo Canyon does not allow DPWs to fill a control room min staff position 
because the postulated worst case dose calculation for control room personnel 
is above 500 mrem.  Similarly, a DPW RP/Chem technician cannot fill one of the 
minimum staffing positions on backshifts or weekends because they are not 
eligible for emergency exposures.  We do not have a formalized process of 
actually suspending qualifications but we have been asked by our Operations 
organization to evaluate available options.

Thanks in advance,

Linda


Linda M. Sewell, CHP
Principal Health Physicist
Pacific Gas & Electric Company
Diablo Canyon Power Plant
MS 119/1/117
PO Box 56
Avila Beach, CA 93424
                                                                                
                                                                
P: 805.545.4315 | F: 805.545.2618| [email protected]<mailto:[email protected]>




PG&E is committed to protecting our customers' privacy. 
To learn more, please visit http://www.pge.com/about/company/privacy/customer/