Hello all. I would like to know how the changes to AP928 has impacted your ALARA planning group for developing monthly dose estimates. The scope freeze has been changed from T-16 to T-10 and schedule freeze from T-6 to T-3. Developing a monthly estimate 6 weeks in advance for Station ALARA Committee approval is a challenge now. Please advise be what challenges your station has had as a result of these milestone changes and what you have done as a result. Thanks
Darin L. Hall ALARA Planner Brunswick Nuclear Plant 623-363-8097 Cell [email protected]