Hello all.  I would like to know how the changes to AP928 has impacted your 
ALARA planning group for developing monthly dose estimates.  The scope freeze 
has been changed from T-16 to T-10 and schedule freeze from T-6 to T-3.  
Developing a monthly estimate 6 weeks in advance for Station ALARA Committee 
approval is a challenge now.  Please advise be what challenges your station has 
had as a result of these milestone changes and what you have done as a result.  
Thanks

Darin L. Hall
ALARA Planner
Brunswick Nuclear Plant
623-363-8097 Cell
[email protected]