Comanche Peak would like to know:

Would you consider building a risk plan based on 05-008, Medium Risk Work 
(Activity involves disassembly, inspection and/or handling components with the 
potential for contamination levels to exceed 200,000 dpm/100 cm². ) for 
diaphragm valves >200K when the diaphragm is being removed, bagged, surface is 
cleaned and diaphragm is replaced.



Thanks!

Shari Mosty