See Vogtle's response below

Michelle Williams
RP Superintendent Support Services
Plant Vogtle Units 1&2
706.848.4236 tel
919.770.7138 cell
[southern_nucl_h_rgb]

From: Powernet <[email protected]> On Behalf Of Mosty, Shari via 
Powernet
Sent: Thursday, June 13, 2019 7:13 AM
To: [email protected]
Cc: Mosty, Shari <[email protected]>
Subject: [Powernet] A Quick Benchmark


 EXTERNAL MAIL: Caution Opening Links or Files

________________________________
*         Station (or fleet if all the same) (Fleet)

*         Do you track PCEs for outages? Yes

*         Do you have goals for all Levels? Just 2/3's? For each level? Level 
1, is not based on 1 per day > level 2/3

*         How do you determine the goals? based on previous outage success and 
work going on for level 1 and standard goal for > level 2/3 is 0

*         Is the requirement for setting a goal proceduralized? no


Shari Mosty
Sr. Health Physicist
Comanche Peak Nuclear Power Plant
6322 N. FM 56
Glen Rose, Texas 76043
254.897.5204
[email protected]<mailto:[email protected]>

Confidentiality Notice: This email message, including any attachments, contains 
or may contain confidential information intended only for the addressee. If you 
are not an intended recipient of this message, be advised that any reading, 
dissemination, forwarding, printing, copying or other use of this message or 
its attachments is strictly prohibited. If you have received this message in 
error, please notify the sender immediately by reply message and delete this 
email message and any attachments from your system.
_______________________________________________
Powernet mailing list
[email protected]
http://hpspowernet.org/mailman/listinfo/powernet_hpspowernet.org

Reply via email to