Some Earned Value Formulas - PMP Study
The PMP exam is big on terminology. These are the basic Earned Value Terms you need to know. If you are studying to pass the PMP exam you should know these by heart and be able to derive them in case you are heartbroken. They really are fairly simple. In order from first to last:
BAC = Budget at Completion (Project budget)
AC = Actual Cost of the Work Performed
EV = Earned Value
EV = Budgeted Cost of the Work Performed
EV = % complete times BAC
PV = Planned Value
PV = Budgeted Cost of the Work Scheduled
CV = Cost Variance
CV = EV AC
CPI = Cost Performance Index
CPI = EV/AC
SV = Schedule Variance
SV = EV PV
SPI = Schedule Performance Index
SPI = EV/PV
EAC = Estimate at Completion
EAC = BAC/CPI
ETC = Estimate to Complete
ETC = EAC AC
VAC = Variance at Completion
VAC = BAC EAC
Note that the acronyms are slightly different from what was used a few years ago and is still widely used by old timers. PMI simplified the terms by dropping a letter here and there. The fundamentals are the same though.
GoodLuck,
PMP Resources
P.S.: HIGH DEMAND RESOURCES FOR PMP EXAM
1000's of PMP Exam Questions, Free Guide for PMP Exam
Loads of Reference Materials, Hidden Entry to Download Area
http://www.pm-best.com/download/?thankyou-page=3
Get Least Expensive 35 Contact Hours
from the comfort of your home
PM Prep Cast
Download PMP Exam Secrets Now
Lowest Price PMP Resources
Free Viral Twitter Blaster Software
Earn $4000 and 9990+ followers per month
on Auto Pilot
--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google Groups "project managment" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to [email protected]
For more options, visit this group at http://groups.google.com/group/project-managment
-~----------~----~----~----~------~----~------~--~---