PMP(r) Daily Wisdom from http://pmbootcamp.org
Ranked #1 by several groups, 2400+ PMP Questions 
PMBOK Latest Edition & thoroughly tested by PMP's
Someone said 'It is most closest to PMP(c) Exam'
7 students also said 'Hope I had found it earlier'
Read PMBOK(c) in 2hrs by reading 310 points from
our Secret Cheat Sheet + Chapterwise for PMP exam
--------------------------------------------------


Qs. All the following statements regarding the creation of duration estimates 
are correct EXCEPT:
A. Mathematical analyses like CPM, GERT, and PERT indicate the dates on which 
the activity can be scheduled, given resource limits and other constraints.
B. Duration compression techniques, including fast tracking and crashing, can 
help in decreasing the project schedule
C. WBS classification allows for useful activity ordering and sorting.
D. The duration of the project is the sum of the duration of all the tasks in 
the project.

If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC2014
Good luck for PMP Exam.

Regards,
PM Guru
[email protected]

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to