PMP(r) Daily Wisdom from http://pmbootcamp.org Ranked #1 by several groups, 2400+ PMP Questions PMBOK Latest Edition & thoroughly tested by PMP's Someone said 'It is most closest to PMP(c) Exam' 7 students also said 'Hope I had found it earlier' Read PMBOK(c) in 2hrs by reading 310 points from our Secret Cheat Sheet + Chapterwise for PMP exam --------------------------------------------------
Qs. A project manager tracks the work of team members using a network logic diagram. Which effect will the presence of an actual finish date have on the calculation of float for the finished activity? A. Finished activities have only float left when they have been completed on schedule. B. Calculating free float and total float is generally not reasonable for finished activities. C. When an activity has been finished, total float gets often converted to become free float. D. When an activity has been finished, float gets often converted to become slack. If you know the answer, reply to your group with reason or follow below instructions for the correct answer - Visit http://pmbootcamp.org - Click on FAQ - Search below keyword - PMBC3005 Good luck for PMP Exam. Regards, PM Guru [email protected] -- You received this message because you are subscribed to the Google Groups "project managment" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/project-managment?hl=en.