Qs. A project manager reported the following Earned value data: PV: $12,400,000 
EV: $14,500,000 AC: $14,500,000 What does this mean?
A. The project is over budget and on schedule.
B. The project is under budget and on schedule
C. The project is on budget, but behind schedule.
D. The project is on budget and ahead of schedule.

If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC4007

This question is sponsored by
Outwitting The PMP Exam
http://clk.im/outwitpmp


Good luck for PMP Exam.

Regards,
PM Guru
[email protected]

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to