PMP(r) Daily Wisdom from http://pmbootcamp.org Ranked #1 by several groups, 2400+ PMP Questions PMBOK Latest Edition & thoroughly tested by PMP's Someone said 'It is most closest to PMP(c) Exam' 7 students also said 'Hope I had found it earlier' Read PMBOK(c) in 2hrs by reading 310 points from our Secret Cheat Sheet + Chapterwise for PMP exam --------------------------------------------------
Qs. A project underwent a major Scope change, which increased cost and work levels. What does this mean for Earned value data? A. The cost baseline will be updated and the new baseline will be the basis for future earned value analysis. B. As baselines should generally not be adjusted, the project is due to exceed its budget from now on. C. There are several reasons to change a baseline, but not scope changes. The project will exceed its budget. D. Earned value analysis becomes useless after a scope change, the technique should not be used any more. If you know the answer, reply to your group with reason or follow below instructions for the correct answer - Visit http://pmbootcamp.org - Click on FAQ - Search below keyword - PMBC4009 This question is sponsored by Outwitting The PMP Exam http://clk.im/outwitpmp Good luck for PMP Exam. Regards, PM Guru [email protected] -- You received this message because you are subscribed to the Google Groups "project managment" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/project-managment?hl=en.