Qs. Post mortem Earned value analysis of a project showed the following data: 
SPI: 1.22 CPI: 1.00 What is this telling you?
A. The entire work of the project has been finished behind schedule and on 
budget.
B. The entire work of the project has been finished ahead of schedule and on 
budget.
C. The project has been terminated before completion. At that time it was ahead 
of schedule and on budget
D. The project has been terminated before completion. At that time it was 
behind schedule and on budget.

If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC5005

This question is sponsored by
Outwitting The PMP Exam
http://clk.im/outwitpmp


Good luck for PMP Exam.

Regards,
PM Guru
[email protected]

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to