Qs. Post-mortem analysis after scheduled finish date of a project shows a CPI 
of 0.8 and an SPI of 1.25. What is a plausible explanation for that?
A. The project was terminated early. At that time, it was over budget and ahead 
of schedule.
B. The project has produced additional deliverables which were originally not 
required.
C. The project has evidently been finished under budget and behind of schedule.
D. The project has evidently been finished over budget and ahead of schedule.

If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC5006

This question is sponsored by
Outwitting The PMP Exam
http://clk.im/outwitpmp


Good luck for PMP Exam.

Regards,
PM Guru
[email protected]

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to