PMP(r) Daily Wisdom from http://pmbootcamp.org Ranked #1 by several groups, 2400+ PMP Questions PMBOK Latest Edition & thoroughly tested by PMP's Someone said 'It is most closest to PMP(c) Exam' 7 students also said 'Hope I had found it earlier' Read PMBOK(c) in 2hrs by reading 310 points from our Secret Cheat Sheet + Chapterwise for PMP exam --------------------------------------------------
Qs. Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that? A. The project was terminated early. At that time, it was over budget and ahead of schedule. B. The project has produced additional deliverables which were originally not required. C. The project has evidently been finished under budget and behind of schedule. D. The project has evidently been finished over budget and ahead of schedule. If you know the answer, reply to your group with reason or follow below instructions for the correct answer - Visit http://pmbootcamp.org - Click on FAQ - Search below keyword - PMBC5006 This question is sponsored by Outwitting The PMP Exam http://clk.im/outwitpmp Good luck for PMP Exam. Regards, PM Guru [email protected] -- You received this message because you are subscribed to the Google Groups "project managment" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/project-managment?hl=en.