Hi All, The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------ Which of the following Enterprise Environmental Factors does not influence the Estimate Activity Durations process? A.) Duration Estimating Databases B.) Project Management Information Systems C.) Productivity Metrics D.) Published Commercial Information ------------------------------ Hint: All of the given choices are valid Enterprise Environmental Factors but which one of them is not relevant to the Estimate Activity Durations process? ------------------------------ All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider. Please click here <http://www.facebook.com/questions/10150261668779970/>for the correct answer and explanation. Until next time, Cornelius Fichtner, PMP President, OSP International LLC - http://www.project-management-prepcast.com -- You received this message because you are subscribed to the Google Groups "project managment" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/project-managment?hl=en.