Hi everyone,

We've had a busy week, and although we're behind schedule, things are
going well. We were mostly rained out on our integration day at Dave's
house, but things look like they're in good shape and we hope to have
tested equivalently to the integration day by the end of the weekend.

Here's this week's schedule:

  Sunday evening: final integration testing at the PSBA at 7:00pm.

  Tuesday: Rocket status update, go/no go call, launch logistics, final
  recovery system packup.

  Thursday: Weather go/no go call

  Friday: pack for Saturday

If you're going to the launch, *please* be at this Tuesday's meeting. If
you can't make it, please let Andrew or Nathan know before Tuesday's
meeting.

See you then, and go team go!

Andrew

-- 
-------------------------------------------------------
Andrew Greenberg

Portland State Aerospace Society (http://psas.pdx.edu/)
and...@psas.pdx.edu  C: 503.708.7711
-------------------------------------------------------

_______________________________________________
psas-team mailing list
psas-team@lists.psas.pdx.edu
http://lists.psas.pdx.edu/mailman/listinfo/psas-team

This list's membership is automatically generated from the memberships of the 
psas-airframe, psas-avionics, and psas-general mail lists. Visit 
http://lists.psas.pdx.edu to individually subscribe/unsubscribe yourself from 
these lists.

Reply via email to