Priorities:
* Getting the last 2-3 tickets for 3.7.0 through
* Double Greenbows (= the double rainbows that appear when all tests
show green)
* Getting ready to release Puppet 3.7 (plan is next week)
* Making sure DOCS team have everything they need
Discussion:
* The last handful of tickets are rattling around on our board, we are
very near completion of 3.7.0.
* We finished the work on the UX research regarding Resource
Expressions, and we made decisions (see PUP-3117) and made adjustments
to the implementation accordingly. The UX research report will be made
public next week (need to anonymize the answers). Additional posts to
come with more details as well.
* We have had a switch over to a new Jenkins CI infrastructure that went
remarkably smooth (kudos to the QA team). While risky as we are close to
a release, there were never really a good time to do this.
* US Folks are off on Monday, and is Andy still walking around somewhere
in Alaska.
- henrik
--
Visit my Blog "Puppet on the Edge"
http://puppet-on-the-edge.blogspot.se/
--
You received this message because you are subscribed to the Google Groups "Puppet
Developers" group.
To unsubscribe from this group and stop receiving emails from it, send an email
to puppet-dev+unsubscr...@googlegroups.com.
To view this discussion on the web visit
https://groups.google.com/d/msgid/puppet-dev/ltr03j%2450l%241%40ger.gmane.org.
For more options, visit https://groups.google.com/d/optout.