Hi All, We start doing the AOO 4.1.1 Full Path Regression Test(FPR) on June 25, here is the weekly update (7/8 - 7/14):
*Test execution:* 1. We have assigned 176 text executions to about 19 volunteers, and completed about 42.6% in execution (69 test executions done). We are behind schedule to finish feature FVT before Aug 8. The planned completion is 50% as of July 14. 2. From below test results distributed among Apps, we need to speed up the testing on Writer(because most of 4.1.1 resolved showstopper bugs are for Writer), and on Impress(because completed percentage is 30.88% which is lower than the average 42.6%) 3. From below test results distributed among platforms, we need to speed up the testing on Redhat Linux 64bit(because completed percentage is 15.56% which is lower than the average 42.6%) and Mac(No progress on Mac!) Test Category Total Not Run Passed Failed Blocked Completed [%] AOO Calc 53 23 28 0 2 56.60 Fidelity 5 4 0 0 1 20.00 AOO Impress 68 47 19 2 0 30.88 AOO Writer 50 27 22 1 9 46.00 Total 176 101 69 3 3 42.60 Platform Total Not Run Passed Failed Blocked Completed [%] MacOS X 32 32 0 0 0 0.00 Redhat Linux 32bit 12 3 8 1 0 75.00 Redhat Linux 64bit 45 38 7 0 0 15.56 Ubuntu Linux 64bit 18 1 13 1 3 94.44 Windows 7 36 15 21 0 0 58.33 Windows 8 17 6 10 1 0 64.71 Windows Server 2012 16 6 10 0 0 62.50 Total 176 101 69 3 3 42.60 *Defect summary:* 1. We have verified 17 of 4.1.1 resolved showstopper bugs (Total 45 as of July 14, increased 10 more since July 7. Backlog is 28 for function bugs) https://issues.apache.org/ooo/buglist.cgi?cmdtype=dorem&list_id=153261&namedcmd=4.1.1_release_blocker%2B%3F&remaction=run&sharer_id=249089 *Issues & quality highlight:* 1. We need more defect verification volunteers, especially bug reporters or bug confirmators who have ever reproduced bugs 2. We need speed up testing on Mac & Redhat Linux 64bit, and on Writer & Impress 3. Testlink system is so slow as to impact test execution's efficiency *Volunteer status: * 1. We have total 19 test execution volunteers joined in FPR execution work since June 24, 8 of 12 new comers in this week are for Redhat Linux. 2. We have total 3 defect verification volunteers joined in 4.1.1 resolved showstopper bug verification work since June 23, but need more as low progress now *Plan for next week:* 1. Continue to do FPR test with M2 2. Remind some test execution volunteers to complete their assignments 3. Continue to organize the FPR test Thank you all for effort provided last week, we have made a good progress, but we still need your continuous help to catch up, especially on Mac/Linux Redhat and Writer/Impress! Regards, Yu Zhen