Here's my proposal for the freeze dates for 9.2: 2024-11-05 Soft feature freeze (all feature changes must be in a pullreq on list by this date) 2024-11-12 Hard feature freeze. Tag rc0 2024-11-19 Tag rc1 2024-11-26 Tag rc2 2024-12-03 Tag rc3 2024-12-10 Release; or tag rc4 if needed 2024-12-17 Release if we needed an rc4
Any objections/suggested tweaks? (I was about 50/50 between this and moving it a week earlier -- the rc4-if-we-need-it date is getting uncomfortably close to Christmas. On this schedule, expect me to be quite strict about what goes into rc2/rc3 :-)) thanks -- PMM