On Mon, 6 Jan 2020 at 15:29, Peter Maydell <peter.mayd...@linaro.org> wrote:
>
> Here's a suggested set of dates for the 5.0 release:
>
> 2020-03-17 softfreeze
> 2020-03-24 hardfreeze/rc0
> 2020-03-31 rc1
> 2020-04-07 rc2
> 2020-04-14 rc3
> 2020-04-21 release, or rc4
> 2020-04-28 release if we needed rc4
>
> (I'm at a conference week of 23-27 March, so possibly rc0
> might get a little delayed if I'm not able to handle
> pullreqs while away, but usually the big rush is for
> softfreeze so I think this should be OK.)
>
> NB: Easter is 10th-13th April, so between rc2 and rc3.
>
> Any opinions/suggested tweaks/etc?
>
> Of course if somebody else wants to do this release cycle
> they can set the dates :-)

Ping? Any opinions? In the absence of complaints I'll just
go with this set of dates...