Hi all, *Weekly Report 4*
*What was done this week?* - Have tested the algorithm of plug-in on various data-sets and the result are what we desired and have their topology preserved. - Tried to add test suites for the plug-in. *What is the plan for next week?* - Try and complete addition of test suites so that we can focus on next steps of the project. *Wiki page : *http://hub.qgis.org/wiki/quantum-gis/nishithm *Code repository :* https://github.com/nishithm/schematization Thanks and regards, Nishith Maheshwari Lab for Spatial Informatics IIIT Hyderabad