install time was A BIT better, layout took some time & as usual the tying up
of cables is what takes the longest. What really sucks is the wait time
between selling them then not being able to get them. They say this will
soon be a thing of the past....... still waiting. That being said the folks
at Enphase are quite helpful.
I'm not sure about the inverters rated performance according to the CEC.
 
 
     <mailto:[email protected]> [email protected]         <http://www.swnl.net/>
www.SWNL.net
           Solarwinds Northernlights   
   Serving Mid Coast Maine & Northern California
     Me.# 207-832-7574  Cl.#  610-517-8401
 
                          Blair "TUMP" May
      ********  MAINE'S CHARTER ********
            NABCEP    "Certified PV Installer" 
   
      ********  MAINE'S CHARTER ********
   Trace Xantrex "Certified" Dealer / Installer"
   
  

-----Original Message-----
From: [email protected]
[mailto:[email protected]] On Behalf Of Marco
Mangelsdorf
Sent: Wednesday, July 22, 2009 12:31 AM
To: 'RE-wrenches'
Subject: [RE-wrenches] Enphase comparison



To those of you who have installed PV systems in, say, the 2-4 kW range
using Enphase inverters, how would you compare the labor time and
installation materials (wire, conduit, hardware, etc.)  to a standard system
design using a single inverter?

 

Longer?  Shorter?  More or less materials?  If either, by what percentage?

 

Thanks,

Marco

ProVision

 

_______________________________________________
List sponsored by Home Power magazine

List Address: [email protected]

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to