Hi Darryl, Most tower companies should supply the structural and foundation design and engineering. The only engineering the installer should need to provide is geotechnical (soils). If the soils are not within the strength parameters that the tower foundation is designed for, you may then need to pony up for foundation re-engineering.
Best, -Kelly Kelly Keilwitz, P.E. Whidbey Sun & Wind, LLC Renewable Energy Systems NABCEP Certified PV Installer WA Electrical Administrator #KEILWKM923RB 987 Wanamaker Rd. Coupeville, WA, 98239 360.678.7131 [email protected] WA Electrical Contractor #WHIDBSW920MS WA General Contractor #WHIDBSW946M1 On 2/24/10 3:34 PM, "Darryl Thayer" <[email protected]> wrote: > HI all > I have a AHJ problem in that he wants to have the tower diagram wet stamped by > a Minnesota PE does anyone have any suggestions? I cant seem to find anyone > with tower experience. > Darryl > > > > _______________________________________________ > List sponsored by Home Power magazine > > List Address: [email protected] > > Options & settings: > http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org > > List-Archive: > http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org > > List rules & etiquette: > www.re-wrenches.org/etiquette.htm > > Check out participant bios: > www.members.re-wrenches.org > _______________________________________________ List sponsored by Home Power magazine List Address: [email protected] Options & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out participant bios: www.members.re-wrenches.org