This doesn't exactly answer your question, but what about doing a
service side tap and avoiding the panel altogether?

 

Jason Szumlanski

Fafco Solar

 

 

From: [email protected]
[mailto:[email protected]] On Behalf Of Eric
Thomas
Sent: Tuesday, September 28, 2010 3:27 PM
To: [email protected]
Subject: [RE-wrenches] Split Panel Interconnection

 

Hello,

We are bidding an 8kW grid tied PV system that will interconnect with a
"split panel". The panel has a main lug on the top portion and branch
circuits on the lower portion. Does anyone have experience with
backfeedig these panels? What's the best method? 

Thanks,

Eric Thomas
Solar Epiphany LLC

_______________________________________________
List sponsored by Home Power magazine

List Address: [email protected]

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to