Alex:

This is all about reducing risk. I include sections specifying that additional charges may apply if:

-We are required to appear at a planning commission, historical preservation or other committee or create additional documents to respond to special requirements.
-We hit bedrock or unmarked private utilities while boring or trenching.
-The customer changes the design.
-The roof has hidden defects.
-The Enphase or other communication medium does not work.
-The materials are delayed due to no fault of mine.

Good luck!

William


At 01:15 PM 10/24/2012, you wrote:
Although, not a specifically a wrenching question, writing solid paperwork directly leads to turning the wrench.

I am looking to update my contract small print. I'm updating a contract that has worked for 35 years, but it is highly reliant on a firm hand shake, so to speak.

In summary, it contains; price, terms of payment, expressed warranty and workmanship manner, not responsible for out of control delays, bid good for 30 days, extras billed on top of this contract, acceptor pays attorneys if it has to go to court for any reason, service percentage for over due balance.

Any suggestions or must-haves?
Anyone writing in consulting charges for "design rights", clause for if you designed something unique for a customer someone else uses your design?

--
Alex Cozine
NABCEP Certified Solar PV Installer™
Journeyman Electrician

Brothers Electric Solar
<http://brotherselectricsolar.com>brotherselectricsolar.com
_______________________________________________
List sponsored by Home Power magazine

List Address: [email protected]

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org


No virus found in this incoming message.
Checked by AVG - www.avg.com
Version: 8.5.455 / Virus Database: 271.1.1/5350 - Release Date: 10/23/12 18:34:00

Miller Solar
Voice :805-438-5600
email: [email protected]
http://millersolar.com
License No. C-10-773985
_______________________________________________
List sponsored by Home Power magazine

List Address: [email protected]

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to