I know I saw a thread on this but I cannot find it in the archive.  I have
inherited a customer that has a four inverter Outback system, 240V 1 Phase,
on a 208Y120V 3 Phase 4 Wire system, that constantly has problems.  A 208V
to 240V 1 phase transformer was installed feeding the input, but the system
still struggles.  Will this system ever work correctly as is, or does it
need to be rewired for 3 phase and use the third inverter as a spare.  This
would include a lot of work rewiring the output panel.  Any ideas?



W.C. (Bill) Turberville P.E.

President



ECE Solar

Electrical Contracting Enterprises LLC

3080 Stage Post Road Suite 107

Bartlett, TN 38133



901-348-9230 ext 101 phone

901-348-2192 fax

901-289-6346 cell

[email protected]
_______________________________________________
List sponsored by Home Power magazine

List Address: [email protected]

Change email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to