Wrenchers, The Ct Utility company CL&P requires the following as part of the verification test. "Because this is a three-phase service, the witness test must also demonstrate that the inverter shuts down upon loss of each individual phase"
Any recommendations on how to do this test safely? Al Frishman AeonSolar (917) 699-6641 - cell (888) 460-2867 www.aeonsolar.com
_______________________________________________ List sponsored by Redwood Alliance List Address: [email protected] Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/[email protected]/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org