I have done some work in central America where there was only a genny down the road that supplied power and it would only run if someone put fuel in it, is this your issue also. Jerry
On Sat, Oct 4, 2014 at 7:37 AM, Conrad Geyser <[email protected]> wrote: > Esteemed wrenchies, > > I'm working on Integrating PV with a group in the Caribbean on commercial > sites with intermittent gird power. Need to be able to work grid tied and > generator tied. No UL 1741. Anybody worked with this? Need some > consulting and/or therapy. > > always a pleasure, > > Conrad > NABCEP PV and thermal > Cotuit Solar LLC, etc. > > > _______________________________________________ > List sponsored by Redwood Alliance > > List Address: [email protected] > > Change listserver email address & settings: > http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org > > List-Archive: > http://www.mail-archive.com/[email protected]/maillist.html > > List rules & etiquette: > www.re-wrenches.org/etiquette.htm > > Check out or update participant bios: > www.members.re-wrenches.org > > >
_______________________________________________ List sponsored by Redwood Alliance List Address: [email protected] Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/[email protected]/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org