James,

I can think of one install I performed in 2017 that was a metal roof over
metal purlins and we opted to through-bolt the entire array using one
installer on a ladder inside and another on the roof.  We employed butyl
mastic and large fender washers to attach a strut frame to the roof, and
then we installed traditional L-feet and rails atop the strut.  I have zero
experience working with tile so I don't know what your best methodology is
there but I can attest that the through-bolting has held up well at that
site the past five years.

Sincerely,
Sam Haraldson

[image: OnSite Energy]
<https://www.google.com/url?q=https://onsiteenergyinc.com/&source=gmail-html&ust=1677085494759000&usg=AOvVaw2NN36GoM1sjnS4RdC8Svt->

SAM HARALDSON
Field Operations Director
(406) 551-6135
1515 N. Rouse Ave Bozeman, MT 59715
Locally owned and operated since 2012
[image: B Corporation]
<https://www.google.com/url?q=https://onsiteenergyinc.com/bcorp&source=gmail-html&ust=1677085494759000&usg=AOvVaw0EluC1lXtz2KlRFag-htKe>
_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: [email protected]

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/[email protected]/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

Reply via email to