Wrenches,
We have a 400 kW ground mount on an east/west slope with shale bedrock at
about 4'. A driven pile system won't work, so we are looking at ground
screws with TerraSmart, but it's a significant price increase. Seems like
the combo of slope (it's upward of 25% and a lot of racking solutions don't
support that) and system size (quite a few racking options aren't available
until you start getting into the .5MW or 1MW range). I don't know if this
is the right place to ask for suggestions, but seemed like a good start!
Thanks for any thoughts
Adam

Adam Katzman (he/him)
Autonomous Energies | Owner/Operator
www.AutonomousEnergies.com <http://www.autonomousenergies.com>
(518) 567-1468
_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: [email protected]

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/[email protected]/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

Reply via email to