I would agree with Richard. as a base we would quote about 2 days per 
master template and a day or two for sub templates. adding on top of 
thatabout 1-2 weeks for project setup-install and what not. You need a 
decent requirements to do the navigation templating and then on top of that 
its time for any bespoke work (.net, php stuff), time for deployments 
etc.... Even for a fairly simple site (say 5 master templates, 10 
subtemplates, navifation and a couple of .net forms), with any UAT and 
deplyment your looking at around 2-3 months, and thats before adding 
content (as thats usually done by the client). 

-- 
You received this message because you are subscribed to the Google Groups 
"RedDot CMS Users" group.
To view this discussion on the web visit 
https://groups.google.com/d/msg/reddot-cms-users/-/-QtGqYz2dugJ.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/reddot-cms-users?hl=en.

Reply via email to