I would agree with Richard. as a base we would quote about 2 days per master template and a day or two for sub templates. adding on top of thatabout 1-2 weeks for project setup-install and what not. You need a decent requirements to do the navigation templating and then on top of that its time for any bespoke work (.net, php stuff), time for deployments etc.... Even for a fairly simple site (say 5 master templates, 10 subtemplates, navifation and a couple of .net forms), with any UAT and deplyment your looking at around 2-3 months, and thats before adding content (as thats usually done by the client).
-- You received this message because you are subscribed to the Google Groups "RedDot CMS Users" group. To view this discussion on the web visit https://groups.google.com/d/msg/reddot-cms-users/-/-QtGqYz2dugJ. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/reddot-cms-users?hl=en.
