Here's a revised proposal:

https://wiki.gnome.org/MichaelCatanzaro/ScheduleTest

After consultation with developers, I decided that leaving only a single week between .0 and .1 would be not enough time, and we have .1 back as far as it can go. So instead of pushing everything two weeks later relative to 3.36, this revised schedule moves things only one week later.

Please let me know if you see anything wrong. Note there is a tarball deadline on a US holiday (July 4), but I assume maintainers will want to release a day or two before the deadline anyway.

Andre, what's required to finalize this?


_______________________________________________
[email protected]
https://mail.gnome.org/mailman/listinfo/release-team
Release-team lurker? Do NOT participate in discussions.