20 April is the new soft freeze deadline. From the Release Schedule [R], we 
learn that features you want to work on after that deadline (and that should 
get into 4.1) need to be in the Feature Plan. [F]

The release team has been asked for a bit more time, there are at least two 
sprints happening during the weekend after the freeze - Kate and Plasma. The 
developers would like to have the opportunity to add stuff that they hadn't 
thought about earlier.

[R] 
http://techbase.kde.org/index.php?title=Schedules/KDE4/4.1_Release_Schedule
[F] http://techbase.kde.org/index.php?title=Schedules/KDE4/4.1_Feature_Plan

Happy hacking :)
-- 
sebas

 http://www.kde.org | http://vizZzion.org |  GPG Key ID: 9119 0EF9 