Hi there,

I'm just not "getting" the whole events and clocks thing. My situation
is that all our shows are pre-recorded (well, let's assume for
simplicity they are!). I have a 2 hour show, some 1 hour shows and
some half-hour shows. The way we have things at the moment is just
putting each show in a cart and creating a log that plays them out to
schedule.

Now, I guess what I *should* have is one Event for each show? And then
what happens with Clocks? Do I have a Clock for each show? Or to cover
each hour? What if I have something going from 1330 to 1430? Do I
split things up? Please don't say "whatever you like" or "whatever
works". I'd really like some suggestions on how *you* would do it.

I'm hoping that if someone can give me some suggestions on the best
way to do this, I'll suddenly "get it"! :-)

Many thanks, Seumas
--
Seumas Mackinnon
"It is in truth not for glory, nor riches, nor honours that we are fighting,
but for freedom -- for that alone, which no honest man gives up but with
life itself." -- Declaration of Arbroath, 1320