That sounds good Matt. I'm glad to hear that those tasks are going to
be a standard part of Ant.
Still, I'd rather defer the download LGPL work to Roller 2.2 and push
Roller 2.1 out now, since the bug list is clear and it's running in
production now. Allen and I are ready to get started with Roller 2.2
work.
Anybody else want to weigh in on this issue.
- Dave
On Dec 21, 2005, at 11:46 AM, Matt Raible wrote:
I have a pretty good amount of experience with Maven 2's Ant Tasks
(which I've heard are going to be a part of Ant 1.7). However, my
vacation just started today and I won't have time to work on this for
a week or two. I'm more than willing to tackle it at the end of the
first week in January.
Matt
On 12/21/05, Dave Johnson <[EMAIL PROTECTED]> wrote:
We're wrapping up Roller 2.1 and Allen and I are starting to work on
our next set of features (due at end of January).
There's one 2.1 "feature" that remains to be done and that's "Download
LGPL dependencies" -- but since we've started to look at alternatives
to our biggest LGPL dependency (i.e. Hibernate), I'm not sure we need
to do this work right now.
Does anybody have the time to do the "Download LGPL dependencies" work
now, or shall we punt it and make preparations for the Roller
2.1-incubating release?
- Dave
PS. here's the release proposal:
http://www.rollerweblogger.org/wiki/Wiki.jsp?
page=Proposal_Roller_2.1_Release