I'd vote for a six months release cycle. ...in case we can actually enforce it.
  ----- Original Message ----- 
  From: Olaf Siejka 
  To: ReactOS Development List 
  Sent: Saturday, October 09, 2010 3:14 PM
  Subject: [ros-dev] ReactOS development cycle


  I think its a good time to discuss current development cycle. 
  It become clear to me, that there is no way we can currently adhere to 3 
months development cycle. Its pointless to stick to something we managed to 
succeed only once or twice. 

  Agreeing with the fact we do need releases, for various reasons, i would like 
to propose a new, longer cycle.


  The most apparent choices to me are 4 and 6 month ones. At least half of the 
cycle would be spent on all out development, with the following half turning 
its concentration to stabilizing trunk, searching for regressions and bugs, 
fixing them. The cycles would be separated by branching the release version. 
The actual release would be taking place on the first month of the NEXT 
DEVELOPMENT cycle. The actual emergency hacking, writing changelog etc. One 
month is more than enough, to release two RC (at the branching and next one - 
after two weeks). End of the month must result in final release. RC should be 
rather released internally for testing purposes on a default iso.


  The actual proposals are:


  4 months:


  month 1: Development on version x. At the same time, the Release x-1 is to be 
final-tested, emergency-hacked, changelogged and shipped. The deadline is end 
of month 1.
  month 2: Development on version x. All development that can affect trunk 
stability, but also will not be shipped with the release X should end or be 
limited to branch only by the end of this month;
  month 3: Switching from development more to stabilizing trunk, searching for 
regressions, fixing bugs. Finalizing sub-projects that are to be included in 
release x; 
  month 4; No new functionality/code, bug-fixing and hunting regressions. This 
month should end with branching for release x;


  6 months:


  month 1: Development on version x. At the same time, the Release x-1 is to be 
final-tested, emergency-hacked, changelogged and shipped. The deadline is end 
of month 1.
  month 2: Development on version x;
  month 3: Development on version x. All development that can affect trunk 
stability, but also will not be shipped with the release X should end or be 
limited to branch only by the end of this month; 
  month 4: Switching from development more to stabilizing trunk, searching for 
regressions, fixing bugs. Ongoing development work only for features that are 
to be shipped with release x;
  month 5: Switching from development more to stabilizing trunk, searching for 
regressions, fixing bugs. Finalizing sub-projects that are to be included in 
release x;
  month 6: No new functionality/code, bug-fixing and hunting regressions. This 
month should end with branching for release x;


------------------------------------------------------------------------------


  _______________________________________________
  Ros-dev mailing list
  Ros-dev@reactos.org
  http://www.reactos.org/mailman/listinfo/ros-dev
_______________________________________________
Ros-dev mailing list
Ros-dev@reactos.org
http://www.reactos.org/mailman/listinfo/ros-dev

Reply via email to