I need to plan some tasks within a nr of timeslots.
Until now a task was always done within the period of one timeslot and I could
validate my rules since a task has a planning variablegetTimeSlot/ setTimeSlot.
Now requirements have changed and a task can take more than one timeslot to
complete.
What is the best way to validate that the task is not started in a timeslot
that would end the task after the last timeslot?
- Timeslots are always equally long (for example a week).
- All timeslots in the list of timeslots are sequential (no gaps).
So if I have a list of timeslots W18, W19, W20, W21 and I have a task taking 3
TimeSlots to complete, it should start in W18 or W19.
Should I create a single planningRange fact, holding the first and last slot?
Any directions would be appreciated.
Regards,
Michiel Vermandel
-----------------
http://www.codessentials.com - Your essential software, for free!
Follow us at http://twitter.com/#!/Codessentials