This is shocking news. 

MLA Dilip could prove that he had th epower to put and
end to corruption and bring peace to Saligao.

Seby Mascarenhas



--- m&m <[EMAIL PROTECTED]> wrote:

> Dear Saligaonettekars,
> 
> Our report on the dangerous way the 11,000 volts,
> underground, 
> power cables are being laid in Saligao, is online. 
> 
> Get a ringside view with 15 pictures  of the action,
> links to the 
> main players and contact details of officials to 
> followup with @ www.anothergoa.blogspot.com
> 
> Below is the text of the report.
> 
> Solidarity.
> 
> M&M.
> ------------------------------------
> 
> Future Shock: GED, L&T And PGCIL Keep An Entire
> Village In 
> Suspense!
> 
> Anytime after their new underground electricity
> cables are 
> charged, residents from Saligao, Goa, may well be in
> for a 
> surprise. And it will not be pleasant, because it
> could shock 
> them into an Intensive Care Unit if not straight
> into the next 
> world. Instead of cool, life-giving water gushing
> from Saligao’s 
> taps, villagers do not know when 11,000 volts (11
> KVA) of raw, 
> electric power will zap and toast them to a crisp.
> The suspense 
> itself is shocking!
> 
> There is a running feud between Larsen & Toubro
> (L&T) [link 
> online] the company that bagged the prestigious
> contract for the 
> underground cabling in Goa and their sub-contractors
> who are 
> actually digging and installing the cables here in
> Saligao. The 
> dispute ensured that the 11 KVA cable criss-crossed
> water 
> pipelines in Tabravaddo, while in neighbouring
> Donvaddo, 
> residents claimed they were laid squarely on top of
> a network of 
> 4 water pipes under a narrow road. No one has a clue
> where the 
> cables are being laid in the rest of the village,
> least of all 
> the local Public Works Department-Water (PWD) [link
> online] that 
> maintains the water pipes in Saligao.
> 
> In this high suspense drama, where the main players
> are the Goa 
> Electricity Department (GED) [link online] as the
> owner of the 
> project, L&T as contractors, with the Power Grid
> Corporation of 
> India Ltd. (PGCIL) [link online] as consultants, no
> one, 
> especially the GED know what is happening.
> 
> There is no one from GED on site to ensure safe
> procedures. When 
> we talked to one engineer from GED, he was shocked
> to hear of 
> the safety measures employed and asked us to write a
> complaint 
> to the engineer looking after the 11 KVA lines in
> this area.
> 
> There also is no coordination between L&T and the
> Telephone
> (BSNL) [link online], PWD-Water and PWD-Roads
> departments. For 
> instance, when the digging was started on our road
> opposite St. 
> Anne's chapel, the local PWD-Water supervisor was
> not called in 
> to point out the exact location of the water pipes.
> 
> L&T have instructed the digging contractors to
> maintain a minimum 
> of 300 mm or 1 foot distance between the cable and
> the nearest 
> water pipeline. "If the distance is not available,
> a partition of loose bricks will be constructed by
> the side of 
> the pipeline to separate the 11 KVA cable", says
> Jayshanker, 
> L&T's engineer in charge of the Saligao project (see
> 
> Jayshanker's diagram of the 300 mm distance).
> 
> We insisted that Santosh Mandrekar, the supervisor
> in charge of 
> PWD's water department in Saligao, meet Jayshanker
> at the site 
> outside our house a few days ago. Mandrekar pointed
> out the 
> future danger of local PWD staff working on a
> damaged pipeline 
> next to the 11 KVA power cable. "If by mistake my
> worker's pick 
> axe digs into the power cable, in a trench filled
> with water, 
> can you imagine what will happen? Not only will my
> worker be 
> electrocuted instantly, but every pipeline and tap
> in the 
> village will immediately be charged with 11,000
> volts of 
> electricity!" (see pics showing leak caused by cable
> digging and 
> emptying of trench after valves were shut)
> 
> Jayshanker assured Mandrekar that adequate
> precautions will be 
> taken and that wherever the11 KVA cable crosses
> water lines, the 
> cable will be put under the pipeline at a safe
> distance. This 
> however does not seem to be happening at all places,
> as the 
> digging contractors are refusing to dig deeper or
> broader to 
> maintain the 300 mm safe distance when they come
> across a water 
> pipeline. It was only when we insisted that they
> reluctantly 
> installed the cables under the pipelines outside our
> house.
> 
> This means that if local citizens do not supervise
> and insist on 
> the 11 KVA cable being laid below the water pipes,
> or a safe 300 
> mm away, we may just have the cable lazily laid
> above them or 
> too close to them. There they will lie in wait, like
> a mass 
> death trap for unsuspecting Saligaokars in future
> (see pictures 
> of cables laid on, side-by-side or just below the
> water pipe).
> 
> Opposite our house we had decided to jump into the
> trench and 
> physically stop the work if better sense did not
> prevail on L&T 
> and its local digging contractors. Some safety
> measures were 
> employed like laying the cables under the pipe
> instead of over, 
> as had been planned. But the safety measures are far
> from 
> adequate as can be seen from the accompanying pics.
> We actually 
> have a potential 'gramicide' (extermination of a
> whole village, 
> where 'gram' means village!).
> 
> We spent 4 entire days to ensure that at least some
> semblance of 
> safety was maintained on the cables being laid from
> St. Anne's 
> Chapel to the transformer by the side of our house.
> Time and 
> time again we have had to liaise between and call
> for common 
> meetings between local PWD staff, digging
> contractors, panchayat 
> member and L&T. And then to the extent humanly
> possible, we 
> actually supervised that the maximum safe distance
> is maintained 
> between the power and water lines.
> 
> Dr. Wilfred D'Souza , our previous MLA and Deputy
> Chief Minister 
> [link online] who brought the underground cabling to
> Saligao has 
> been informed. Bhola Ghadi, the local panchayat
> member is aware 
> of this dangerous situation and is with the
> villagers to avert 
> any potential danger to lives in future. We raised
> the issue at 
> the Gram Sabha yesterday and asked for a Panchayat
> member to 
> oversee the entire operation in the village. Last
> evening, we 
> also met the new MLA, Dilip Parulekar [link online]
> who 
=== message truncated ===



 
____________________________________________________________________________________
Don't get soaked.  Take a quick peak at the forecast
with the Yahoo! Search weather shortcut.
http://tools.search.yahoo.com/shortcuts/#loc_weather
_______________________________________________
Saligao 403511 website http://saligao.goa-india.org
Saligaonet mailing list