Should Start On: => Wed 04/06/2005 at 00:00
Should be Finished on: => Wed 04/06/2005 at 00:00
Percent Complete: 0% => 50%
Assigned to: None => Zeus
_______________________________________________________
Follow-up Comment #1:
Hi,
I'm evaluating the project you submitted for approval in Savannah.
As you wrote, you do not have source code yet, exist a process that we
can use to approve your project and is approved it as without source
code, this means that we will review your source code in a month(more
or less) looking for any kind of problem that we didn't catch in the
approval process, are you agree with this point?