Re: ITSM 8 Unpatched Version Install

2012-10-20 Thread Joshua Taylor
I had AR, Atrium, ITSM, SLM, and SRM all installed in about 7 hours.  For ITSM 
I selected all 5 modules to install at once and it took about 2 hours.  I was 
using Windows 2008 64 bit.

From: Action Request System discussion list(ARSList) [arslist@ARSLIST.ORG] on 
behalf of Bhupesh Gupta [gupta.bhupesh3...@gmail.com]
Sent: Saturday, October 20, 2012 9:37 PM
To: arslist@ARSLIST.ORG
Subject: ITSM 8 Unpatched Version Install

Hi Friends -

How long does an ITSM installation take when all modules are selected at one go?

For me , its 21 hours and installation is still going on?

As an work-around my colleagues tried to install module by module
which seems to take less time.


Kindly Suggest.

Is there any docs, what BMC recommendation on timelines of installation is?

--
Regards,
Bhupesh Gupta

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug12 www.wwrug12.com ARSList: Where the Answers Are

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug12 www.wwrug12.com ARSList: Where the Answers Are


AIF and Overlays

2012-10-19 Thread Joshua Taylor
Does anyone know of a way to create overlays of all of the OOB AIF workflow at 
once?  I am not looking forward to right clicking on 179 AL's and selecting 
'Create Overlay'.  Normally I would just make copies and use these as I did in 
pre 7.6.04, however BMC is recommending that I not do this.  This in a brand 
new 8.0 environment (All modules) and is a dev box so I am open to any sort of 
suggestion even if there is the chance it could hose the system as I do have 
several backups I can restore to.

Thanks,
Josh



___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug12 www.wwrug12.com ARSList: Where the Answers Are


Re: AIF and Overlays

2012-10-19 Thread Joshua Taylor
Hey Tauf,

I am creating AIF's for services that have criteria that cannot be met by a 
standard SRD.  BMC now recommends that instead of copying the OOB AL's, 
Filters, and Guides (which is what BMC recommended be done before overlays were 
introduced), you should attach your AIF's to the OOB workflow.  The issue is 
that in order to use 'Best Practice Customization Mode' one must first create 
overlays of all OOB workflow that is to be modified, or change them to Custom 
forms (which defeats the purpose of overlays and will be a major headache come 
upgrade/patch time).  So at this point I am faced with the daunting task of 
clicking and modifying each piece of workflow at least once if not twice.  And 
considering there are 179 Active Links, 20 Filters, 20 Active Link Guides, and 
2 Filter Guides associated with the form 
SRS:AdvancedInterface_WithBackendMapping I am looking at an extremely long 
process to create my first AIF.  Once I have the first AIF done then any future 
ones should be quite easy as I can edit multiple active links and filters all 
at once.

Hope this makes sense.  I am going to attempt to create an overlay of the SRM 
application and will keep everyone updated as to how it goes.

Thanks,
Josh

From: Action Request System discussion list(ARSList) 
[mailto:arslist@ARSLIST.ORG] On Behalf Of Tauf Chowdhury
Sent: Friday, October 19, 2012 2:41 PM
To: arslist@ARSLIST.ORG
Subject: Re: AIF and Overlays

**
Josh,
Not providing a solution here but looking for the reasoning behind this out of 
curiosity.
I think 8.0 gives you the ability to overlay an entire application which could 
do what you are saying.

Sent from my iPhone

On Oct 19, 2012, at 1:27 PM, Joshua Taylor 
joshua.tay...@tn.govmailto:joshua.tay...@tn.gov wrote:
**
Does anyone know of a way to create overlays of all of the OOB AIF workflow at 
once?  I am not looking forward to right clicking on 179 AL's and selecting 
'Create Overlay'.  Normally I would just make copies and use these as I did in 
pre 7.6.04, however BMC is recommending that I not do this.  This in a brand 
new 8.0 environment (All modules) and is a dev box so I am open to any sort of 
suggestion even if there is the chance it could hose the system as I do have 
several backups I can restore to.

Thanks,
Josh


_attend WWRUG12 www.wwrug.comhttp://www.wwrug.com ARSlist: Where the Answers 
Are_
_attend WWRUG12 www.wwrug.comhttp://www.wwrug.com ARSlist: Where the Answers 
Are_

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug12 www.wwrug12.com ARSList: Where the Answers Are


Re: AIF and Overlays

2012-10-19 Thread Joshua Taylor
Ok so I tried creating an overlay of the SRM application and it did what I 
thought it would.  It created the overlay of just the application itself.  It 
did not touch the forms or any of the workflow associated with it.  So at this 
point I am back to touching each piece of workflow individually.  I may open a 
ticket with BMC on Monday about it to see what they say I should be doing since 
it is their recommendation that I use the OOB workflow instead of making copies 
like we did in the pre 7.6.04 SRM system.

From: Joshua Taylor
Sent: Friday, October 19, 2012 3:52 PM
To: 'arslist@ARSLIST.ORG'
Subject: RE: AIF and Overlays

Hey Tauf,

I am creating AIF's for services that have criteria that cannot be met by a 
standard SRD.  BMC now recommends that instead of copying the OOB AL's, 
Filters, and Guides (which is what BMC recommended be done before overlays were 
introduced), you should attach your AIF's to the OOB workflow.  The issue is 
that in order to use 'Best Practice Customization Mode' one must first create 
overlays of all OOB workflow that is to be modified, or change them to Custom 
forms (which defeats the purpose of overlays and will be a major headache come 
upgrade/patch time).  So at this point I am faced with the daunting task of 
clicking and modifying each piece of workflow at least once if not twice.  And 
considering there are 179 Active Links, 20 Filters, 20 Active Link Guides, and 
2 Filter Guides associated with the form 
SRS:AdvancedInterface_WithBackendMapping I am looking at an extremely long 
process to create my first AIF.  Once I have the first AIF done then any future 
ones should be quite easy as I can edit multiple active links and filters all 
at once.

Hope this makes sense.  I am going to attempt to create an overlay of the SRM 
application and will keep everyone updated as to how it goes.

Thanks,
Josh

From: Action Request System discussion list(ARSList) 
[mailto:arslist@ARSLIST.ORG] On Behalf Of Tauf Chowdhury
Sent: Friday, October 19, 2012 2:41 PM
To: arslist@ARSLIST.ORGmailto:arslist@ARSLIST.ORG
Subject: Re: AIF and Overlays

**
Josh,
Not providing a solution here but looking for the reasoning behind this out of 
curiosity.
I think 8.0 gives you the ability to overlay an entire application which could 
do what you are saying.

Sent from my iPhone

On Oct 19, 2012, at 1:27 PM, Joshua Taylor 
joshua.tay...@tn.govmailto:joshua.tay...@tn.gov wrote:
**
Does anyone know of a way to create overlays of all of the OOB AIF workflow at 
once?  I am not looking forward to right clicking on 179 AL's and selecting 
'Create Overlay'.  Normally I would just make copies and use these as I did in 
pre 7.6.04, however BMC is recommending that I not do this.  This in a brand 
new 8.0 environment (All modules) and is a dev box so I am open to any sort of 
suggestion even if there is the chance it could hose the system as I do have 
several backups I can restore to.

Thanks,
Josh


_attend WWRUG12 www.wwrug.comhttp://www.wwrug.com ARSlist: Where the Answers 
Are_
_attend WWRUG12 www.wwrug.comhttp://www.wwrug.com ARSlist: Where the Answers 
Are_

___
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
attend wwrug12 www.wwrug12.com ARSList: Where the Answers Are