Re: Tuscany Board Report is due

2012-05-10 Thread ant elder
Thats a little misleading about Beta4 and 2.0. The Beta4 release never
happened and there's been no talk yet of a 2.0 RC2 and no commits
towards that. I see the report is already submitted now so i guess i
don't object too much but I probably would in future.

   ...ant

On Tue, May 8, 2012 at 6:53 PM, Luciano Resende luckbr1...@gmail.com wrote:
 Looking into this quarter board report, and I see couple things to report

 - Tuscany 2.0 Beta4 release was approved, and the community is working
 on the RC2 of the official 2.0 release.
 - Tuscany community engaged with students as part of GSoC 2012, but
 the candidate had proposed ideas for multiple Apache projects and the
 Tuscany one was not selected.
 - The Tuscany PMC voted on a new policy on election and rotation of
 Project Chairs, and also recommended a new project Chair which got
 approved by the Board last month.

 Anything else that should be mentioned ?

 --
 Luciano Resende
 http://people.apache.org/~lresende
 http://twitter.com/lresende1975
 http://lresende.blogspot.com/


Re: Tuscany Board Report is due

2012-05-08 Thread Raymond Feng
It looks good.

Thanks,
Raymond

On May 8, 2012, at 10:53 AM, Luciano Resende wrote:

 Looking into this quarter board report, and I see couple things to report
 
 - Tuscany 2.0 Beta4 release was approved, and the community is working
 on the RC2 of the official 2.0 release.
 - Tuscany community engaged with students as part of GSoC 2012, but
 the candidate had proposed ideas for multiple Apache projects and the
 Tuscany one was not selected.
 - The Tuscany PMC voted on a new policy on election and rotation of
 Project Chairs, and also recommended a new project Chair which got
 approved by the Board last month.
 
 Anything else that should be mentioned ?
 
 -- 
 Luciano Resende
 http://people.apache.org/~lresende
 http://twitter.com/lresende1975
 http://lresende.blogspot.com/



Tuscany board report is due

2012-02-07 Thread ant elder
The Tuscany board report is due this week, i'll prepare a draft but
let me know if there is something you want mentioned.

   ...ant


Re: Tuscany board report is due

2012-02-07 Thread Simon Laws
On Tue, Feb 7, 2012 at 11:44 AM, ant elder ant.el...@gmail.com wrote:
 The Tuscany board report is due this week, i'll prepare a draft but
 let me know if there is something you want mentioned.

   ...ant

The only thing that comes to mind is the addition of a committer.

Simon

-- 
Apache Tuscany committer: tuscany.apache.org