Re: [O] Define resources in ox-taskjuggler

2014-06-30 Thread Christian Egli
Johan Ekh ekh.jo...@gmail.com writes:


 Error: crc is not a defined resource

 I've read some documentation/tutorials and I've searched this list but
 I did not find an answer. Can anyone of you gurus see emmediately what
 is wrong or at least point me in the right direction?

Isn't this just a question of capitalization? In other words try to
define the resource_id lowercase crc.

HTH
Christian

-- 
Christian Egli
Swiss Library for the Blind, Visually Impaired and Print Disabled
Grubenstrasse 12, CH-8045 Zürich, Switzerland




[O] Define resources in ox-taskjuggler

2014-05-27 Thread Johan Ekh
Hi all

I try to use ox-taskjuggler but I'm doing something wrong. I want to
allocate resources to different tasks (see sample code below) but I get the
error:

Error: crc is not a defined resource

I've read some documentation/tutorials and I've searched this list but I
did not find an answer. Can anyone of you gurus see emmediately what is
wrong or at least point me in the right direction?

Best regards
Johan


 Activities :taskjuggler_project:
 :PROPERTIES:
 :start:2014-03-31
 :END:
* Project Management   :0010:
  :PROPERTIES:
  :start:2014-03-31
  :Duration: 200d
  :allocate: crc
  :END:





 Resources   :taskjuggler_resource:
* CRC
  :PROPERTIES:
  :resource_id: CRC
  :END: