Re: [onap-discuss] Guidelines for Casablanca Release Planning

2018-06-28 Thread gildas.lani...@huawei.com
Hi Alex, Ajay, Scott, Vimal, Shekar, Benjamin, Bin, Ramki, Raghu, Jason, 
Stephen, Chris, Helen, Tao,

This email is primarily intended to the Functional Requirement, Non Functional 
Requirements and Use Cases Owner.
On today TSC meeting, the TSC decided to postpone the M1 milestone to Monday, 
July 2 at 6 am PDT in order to allow these owners to reach out to PTLs to 
clarify the requirements so the PTLs can commit accordingly.
There was a discussion on which requirements to focus on. Let's be realistic, 
we won't able to achieve everything in Casablanca and thus while at Beijing 
last week it was requested to Service Provider to provide their priorities. 
Looking at the outcome by the number of 1's, 2's and 3's, the following 
priority appears:

1.   Scaling

2.   Change Management

3.   "5G/PNF" and "Centralized Representation and Consistent ID of Cloud 
Regions" (same ranking)

4.   HPA. Note: During TSC meeting, Alex Vul committed to assign as many 
resource necessary to complete HPA in Casablanca Release.

5.   5G/performance Analysis and Optimization

6.   EA/Cloud Infrastructure for Distributed Edge Clouds

7.   5G/Network slicing (withdraw by owner)

There were also a concern from the TSC that currently there is no single 
requirement that could be delivered because teams have spread out their 
resources. We are hoping the above ranking will help to ensure end to end 
deliver within Casablanca release.

@PTLs,

If not already done, please update the centralized Maturity 
Platform 
table and the outcome of the discussion with the Owner in 
wiki.

Let me know if you have any question, I will be glad to help.

Thanks,
Gildas
ONAP Release Manager
1 415 238 6287

From: Gildas Lanilis
Sent: Thursday, June 21, 2018 4:26 PM
To: onap-rele...@lists.onap.org
Cc: onap-...@lists.onap.org; onap-discuss@lists.onap.org
Subject: Guidelines for Casablanca Release Planning
Importance: High

Hi PTLS,

As you know M1 release planning for Casablanca release is scheduled for next 
week on Thursday, June 28.
As usual, both the Project Plan [0] and Project checklist [1] templates have to 
be filled out.
We had an intensive week here in Beijing discussing Casablanca release, find 
below some guidelines to help on scoping.

>From a requirement perspective, at a high level the Casablanca Release 
>Requirements 
>summarizes the Use Case, the functional and the non-functional requirements. 
>When it comes to the scoping exercise, here are a couple of considerations:

1)  The over-arching theme for Casablanca is deployability

2)  For the Functional requirement, to help out to prioritize, the TSC has 
asked each Service Provider to prioritize the requirements. It looks to me that 
Change Management and Scaling are leading the way. (details are 
posted)

3)  2 new Use Cases have been presented: CCVPN and OSAM. These 2 use cases 
are contingent to  add resources to the impacted project team to develop the 
functionalities and Integration Team bandwidth to perform testing.

4)  For the non-functional, S3P, Security and Architecture Alignment are 
important to take into account as well in the scoping exercise.

We will all meet on Monday at the PTL meeting to understand what can be 
realistically scope in Casablanca timeline.
Hope this helps.

[0]: Project Plan template: 
https://wiki.onap.org/display/DW/Release+Planning+Template
[1]: Project Checklist template: 
https://wiki.onap.org/display/DW/Deliverables+for+Planning+Milestone+Checklist+Template

Thanks,
Gildas

[HuaweiLogowithName]
Gildas Lanilis
ONAP Release Manager
Santa Clara CA, USA
gildas.lani...@huawei.com
Mobile: 1 415 238 6287


-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.

View/Reply Online (#10678): https://lists.onap.org/g/onap-discuss/message/10678
Mute This Topic: https://lists.onap.org/mt/22531454/21656
Group Owner: onap-discuss+ow...@lists.onap.org
Unsubscribe: https://lists.onap.org/g/onap-discuss/unsub  
[arch...@mail-archive.com]
-=-=-=-=-=-=-=-=-=-=-=-



Re: [onap-discuss] Guidelines for Casablanca Release Planning

2018-06-26 Thread BHOJAN, SUMITHRA
Hi,

For OSAM use case, we are making use of PNF capability (I believe that's  part 
of Beijing and Casablanca scope) similar to 5G DU use case. Hence no new 
efforts/impacts to ONAP components were identified with the architecture team.

Thanks,

Sumithra Bhojan
AT - Principal Member of Tech Staff
O-248-344-1866
M-248-719-4612



From: Gildas Lanilis 
Sent: Monday, June 25, 2018 2:00 PM
To: onap-rele...@lists.onap.org; LinMeng ; 
Zengjianguo (OSS Design) ; BHOJAN, SUMITHRA 
; HALLAHAN, RYAN ; b...@eliacik.com; Yunxia 
Chen ; LEFEVRE, CATHERINE 
Cc: onap-...@lists.onap.org; onap-discuss@lists.onap.org
Subject: RE: Guidelines for Casablanca Release Planning

Hi,

This is email is intended to clarify on the needs for coding activities for 
both  CCVPN and OSAM Use Cases.
While at Beijing last week, I heard that both use cases do NOT need coding 
activities but are contingent on adding resources on impacted project and 
Integration Team agreement.
This morning during PTLs meeting the above statement was challenged in a sense 
of on why adding resources on a use case that is presented as no coding 
activities.

May I ask the use case owner to confirm they do not expect coding activities 
and the activities of these resources. I would recommend to reach out to PTLs 
to back up their analysis.
For CCVPN, I expect a response from either Lin Meng or Jianguo Zeng, for OSAM 
from Sumithra Bhojan, Bora Eliacik or Ryan Hallahan

Please add your comments directly in wiki page at 
https://wiki.onap.org/display/DW/Casablanca+Release+Requirements.
 That will help PTLs for M1 scoping.

Thanks,
Gildas
ONAP Release Manager
1 415 238 6287

From: Gildas Lanilis
Sent: Thursday, June 21, 2018 4:26 PM
To: onap-rele...@lists.onap.org
Cc: onap-...@lists.onap.org; 
onap-discuss@lists.onap.org
Subject: Guidelines for Casablanca Release Planning
Importance: High

Hi PTLS,

As you know M1 release planning for Casablanca release is scheduled for next 
week on Thursday, June 28.
As usual, both the Project Plan [0] and Project checklist [1] templates have to 
be filled out.
We had an intensive week here in Beijing discussing Casablanca release, find 
below some guidelines to help on scoping.

>From a requirement perspective, at a high level the Casablanca Release 
>Requirements
> summarizes the Use Case, the functional and the non-functional requirements. 
>When it comes to the scoping exercise, here are a couple of considerations:

  1.  The over-arching theme for Casablanca is deployability
  2.  For the Functional requirement, to help out to prioritize, the TSC has 
asked each Service Provider to prioritize the requirements. It looks to me that 
Change Management and Scaling are leading the way. (details are 
posted)
  3.  2 new Use Cases have been presented: CCVPN and OSAM. These 2 use cases 
are contingent to  add resources to the impacted project team to develop the 
functionalities and Integration Team bandwidth to perform testing.
  4.  For the non-functional, S3P, Security and Architecture Alignment are 
important to take into account as well in the scoping exercise.

We will all meet on Monday at the PTL meeting to understand what can be 
realistically scope in Casablanca timeline.
Hope this helps.

[0]: Project Plan template: 
https://wiki.onap.org/display/DW/Release+Planning+Template
[1]: Project Checklist template: 
https://wiki.onap.org/display/DW/Deliverables+for+Planning+Milestone+Checklist+Template

Thanks,
Gildas

[HuaweiLogowithName]
Gildas Lanilis
ONAP Release Manager
Santa Clara CA, USA

Re: [onap-discuss] Guidelines for Casablanca Release Planning

2018-06-25 Thread gildas.lani...@huawei.com
Hi,

This is email is intended to clarify on the needs for coding activities for 
both  CCVPN and OSAM Use Cases.
While at Beijing last week, I heard that both use cases do NOT need coding 
activities but are contingent on adding resources on impacted project and 
Integration Team agreement.
This morning during PTLs meeting the above statement was challenged in a sense 
of on why adding resources on a use case that is presented as no coding 
activities.

May I ask the use case owner to confirm they do not expect coding activities 
and the activities of these resources. I would recommend to reach out to PTLs 
to back up their analysis.
For CCVPN, I expect a response from either Lin Meng or Jianguo Zeng, for OSAM 
from Sumithra Bhojan, Bora Eliacik or Ryan Hallahan

Please add your comments directly in wiki page at 
https://wiki.onap.org/display/DW/Casablanca+Release+Requirements. That will 
help PTLs for M1 scoping.

Thanks,
Gildas
ONAP Release Manager
1 415 238 6287

From: Gildas Lanilis
Sent: Thursday, June 21, 2018 4:26 PM
To: onap-rele...@lists.onap.org
Cc: onap-...@lists.onap.org; onap-discuss@lists.onap.org
Subject: Guidelines for Casablanca Release Planning
Importance: High

Hi PTLS,

As you know M1 release planning for Casablanca release is scheduled for next 
week on Thursday, June 28.
As usual, both the Project Plan [0] and Project checklist [1] templates have to 
be filled out.
We had an intensive week here in Beijing discussing Casablanca release, find 
below some guidelines to help on scoping.

>From a requirement perspective, at a high level the Casablanca Release 
>Requirements 
>summarizes the Use Case, the functional and the non-functional requirements. 
>When it comes to the scoping exercise, here are a couple of considerations:

1)  The over-arching theme for Casablanca is deployability

2)  For the Functional requirement, to help out to prioritize, the TSC has 
asked each Service Provider to prioritize the requirements. It looks to me that 
Change Management and Scaling are leading the way. (details are 
posted)

3)  2 new Use Cases have been presented: CCVPN and OSAM. These 2 use cases 
are contingent to  add resources to the impacted project team to develop the 
functionalities and Integration Team bandwidth to perform testing.

4)  For the non-functional, S3P, Security and Architecture Alignment are 
important to take into account as well in the scoping exercise.

We will all meet on Monday at the PTL meeting to understand what can be 
realistically scope in Casablanca timeline.
Hope this helps.

[0]: Project Plan template: 
https://wiki.onap.org/display/DW/Release+Planning+Template
[1]: Project Checklist template: 
https://wiki.onap.org/display/DW/Deliverables+for+Planning+Milestone+Checklist+Template

Thanks,
Gildas

[HuaweiLogowithName]
Gildas Lanilis
ONAP Release Manager
Santa Clara CA, USA
gildas.lani...@huawei.com
Mobile: 1 415 238 6287


-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.

View/Reply Online (#10552): https://lists.onap.org/g/onap-discuss/message/10552
Mute This Topic: https://lists.onap.org/mt/22531454/21656
Group Owner: onap-discuss+ow...@lists.onap.org
Unsubscribe: https://lists.onap.org/g/onap-discuss/unsub  
[arch...@mail-archive.com]
-=-=-=-=-=-=-=-=-=-=-=-



[onap-discuss] Guidelines for Casablanca Release Planning

2018-06-21 Thread gildas.lani...@huawei.com
Hi PTLS,

As you know M1 release planning for Casablanca release is scheduled for next 
week on Thursday, June 28.
As usual, both the Project Plan [0] and Project checklist [1] templates have to 
be filled out.
We had an intensive week here in Beijing discussing Casablanca release, find 
below some guidelines to help on scoping.

>From a requirement perspective, at a high level the Casablanca Release 
>Requirements 
>summarizes the Use Case, the functional and the non-functional requirements. 
>When it comes to the scoping exercise, here are a couple of considerations:

1)  The over-arching theme for Casablanca is deployability

2)  For the Functional requirement, to help out to prioritize, the TSC has 
asked each Service Provider to prioritize the requirements. It looks to me that 
Change Management and Scaling are leading the way. (details are 
posted)

3)  2 new Use Cases have been presented: CCVPN and OSAM. These 2 use cases 
are contingent to  add resources to the impacted project team to develop the 
functionalities and Integration Team bandwidth to perform testing.

4)  For the non-functional, S3P, Security and Architecture Alignment are 
important to take into account as well in the scoping exercise.

We will all meet on Monday at the PTL meeting to understand what can be 
realistically scope in Casablanca timeline.
Hope this helps.

[0]: Project Plan template: 
https://wiki.onap.org/display/DW/Release+Planning+Template
[1]: Project Checklist template: 
https://wiki.onap.org/display/DW/Deliverables+for+Planning+Milestone+Checklist+Template

Thanks,
Gildas

[HuaweiLogowithName]
Gildas Lanilis
ONAP Release Manager
Santa Clara CA, USA
gildas.lani...@huawei.com
Mobile: 1 415 238 6287


-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.

View/Reply Online (#10504): https://lists.onap.org/g/onap-discuss/message/10504
Mute This Topic: https://lists.onap.org/mt/22531454/21656
Group Owner: onap-discuss+ow...@lists.onap.org
Unsubscribe: https://lists.onap.org/g/onap-discuss/unsub  
[arch...@mail-archive.com]
-=-=-=-=-=-=-=-=-=-=-=-