Hi All, We started doing the AOO 4.1.1 Full Path Regression Test(FPR) on June 25, here is the weekly update (7/15 - 7/20):
*Test execution:*1. We have assigned 176 text executions to about 20 volunteers, and completed about 50.6% in execution (89 test executions done). We are behind schedule to finish feature FVT before Aug 8. The planned completion is 67.8% as of July 20. 2. From below test results distributed among Apps, we have made progress in testing on Writer, but still need to speed up testing on Impress(because completed percentage is 35.29% which is lower than the average 50.6%) 3. From below test results distributed among platforms, we need to speed up the testing on Redhat Linux 64bit(because completed percentage is 28.89% which is lower than the average 50.6%) and Mac(No progress on Mac!!) Test Category Total Not Run Passed Failed Blocked Completed [%] AOO Calc 53 23 28 0 2 56.60 Fidelity 5 3 1 0 1 40.00 AOO Impress 68 44 21 3 0 35.29 AOO Writer 50 17 32 1 0 66.00 Total 176 87 82 4 3 50.60 Platform Total Not Run Passed Failed Blocked Completed [%] MacOS X 32 32 0 0 0 0.00 Redhat Linux 32bit 12 3 8 1 0 75.00 Redhat Linux 64bit 45 32 12 1 0 28.89 Ubuntu Linux 64bit 18 1 13 1 3 94.44 Windows 7 36 7 29 0 0 80.56 Windows 8 17 6 10 1 0 64.71 Windows Server 2012 16 6 10 0 0 62.50 Total 176 87 82 4 3 50.60 *Defect summary:* 1. We have verified 23 of 4.1.1 resolved showstopper bugs (Total 51 as of July 14, increased 6 more since July 14. Backlog is 28 for function bugs) https://issues.apache.org/ooo/buglist.cgi?cmdtype=dorem&list_id=153261&namedcmd=4.1.1_release_blocker%2B%3F&remaction=run&sharer_id=249089 *Issues & quality highlight:* 1. We need more defect verification volunteers, especially bug reporters or bug confirmators who have ever reproduced bugs 2. We(test cases assignees) need speed up testing on Mac & Redhat Linux 64bit, and on Impress *Volunteer status: * 1. We have total 20 test execution volunteers joined in FPR execution work since June 24, 2 new comers in this week are from Apache OpenOffice Forum. 2. We have total 5 defect verification volunteers joined in 4.1.1 resolved showstopper bug verification work since June 23, 2 new comers in this week are from Apache OpenOffice Forum, but need more as low progress now *Plan for next week:* 1. Continue to do FPR test with M2 and M3 and bug verification 2. Remind some test execution volunteers to complete their assignments 3. Continue to organize the FPR test and bug verification 4. I (Fan, Yuzhen) will be on vacation, may check email occasionally Thank you all for effort provided last week, we need your continuous help to catch up, especially on Mac/Linux Redhat and Impress, as well as the bug verification! Regards, Yu Zhen