Re: [Tails-dev] Next release: process, schedule and iceweasel backports

2012-09-27 Thread intrigeri
Ague Mill wrote (26 Sep 2012 13:48:11 GMT) :
 October 9th:  0.14 freeze + release of RC1.
 October 23th: ESR backport is (hopefully) available.
 October 25th: release of RC2.
 October 30th: release of 0.14.

 Fine with me.

Suits me well.

Cheers,
-- 
  intrigeri
  | GnuPG key @ https://gaffer.ptitcanardnoir.org/intrigeri/intrigeri.asc
  | OTR fingerprint @ https://gaffer.ptitcanardnoir.org/intrigeri/otr.asc
___
tails-dev mailing list
tails-dev@boum.org
https://mailman.boum.org/listinfo/tails-dev


Re: [Tails-dev] Next release: process, schedule and iceweasel backports

2012-09-26 Thread anonym
24/09/12 23:11, intrigeri wrote:
 Hi,
 
 whoever is the Release Manager for the current release cycle: please
 announce the freeze / RC / etc. dates ASAP. If I'm not mistaken, and
 if we don't change the release schedule this time, we're supposed to
 freeze in *one* week. But well, this is subject to change.

Indeed. Looking at my own schedule I saw that this is the case, which I
must say took me a bit my surprise given how recently we released 0.13...

 I think we're supposed to release on week 43, but... how do we deal,
 next time, with an unpredictable iceweasel backports schedule?
 
 I'm happy to focus on our APT repository for the next cycle, and it
 looks like bertagaz is making great progress on the build our own
 iceweasel front, but still, I'd rather not see us assume we'll be
 autonomous in this area in time for the current release cycle.
 
 So, for the current cycle, I suggest we patch our draft release
 schedule from the theoretical:
 
 /   3w\/   2w /2|5d\
 major freeze  firefox
 release   RC1 ESR
 | |   |
 | |   | RC2 release
 | |   | |   |
 ↓ ↓   ↓ ↓   ↓
 ._._._._._._.
 0 1 2 3 4 5 6
 
 
 To the more realistic:
 
 /   3w\/   2w /2|5d\
 major freeze  ESR
 release   RC1 backport is available
 | |   |
 | firefox |
 | ESR is out  |
 | |   |
 | |   | RC2 release
 | |   | |   |
 ↓ ↓   ↓ ↓   ↓
 ._._._._._._.
 0 1 2 3 4 5 6
 
 ??
 
 (This implies releasing two weeks later than planned, that is week 45.
 Also, this assumes the backport is available two weeks after ESR is
 released. Yeah, that's way too late, but we'll soon be able to
 do better.)

Unless we can get some sort of promise from Mike Hommey that the next
Iceweasel ESR will be backported earlier than previously, your proposal
indeed seems unavoidable.

 To end with, given the amount of nice stuff we're currently merging
 into devel, I'd be sad to see this wait until December before being
 shipped to users, and I'm starting to wonder if we should not make the
 next release a major one. That could be Tails 0.14. How crazy does
 that sound?

Not crazy at all. The release cycle/schedule we decided on was a
failure, so I see no reason to stick with it. Well, failure is a bit
hard, but let's say premature; once we have our infrastructure ready
so we don't have to depend on external parties' timely packaging I think
it'll be great to return back to.

*If* we indeed choose to do this I suppose that would push the Tails
0.14 freeze date to the next Firefox ESR release date, which is October
9th (essentially two weeks from now), so:

October 9th:  0.14 freeze + release of RC1.
October 23th: ESR backport is (hopefully) available.
October 25th: release of RC2.
October 30th: release of 0.14.

Cheers!



signature.asc
Description: OpenPGP digital signature
___
tails-dev mailing list
tails-dev@boum.org
https://mailman.boum.org/listinfo/tails-dev


Re: [Tails-dev] Next release: process, schedule and iceweasel backports

2012-09-26 Thread Ague Mill
On Wed, Sep 26, 2012 at 03:10:36PM +0200, anonym wrote:
  To end with, given the amount of nice stuff we're currently merging
  into devel, I'd be sad to see this wait until December before being
  shipped to users, and I'm starting to wonder if we should not make the
  next release a major one. That could be Tails 0.14. How crazy does
  that sound?
 
 Not crazy at all.

I'm all in for a major release. I'd really like it to include
feature/multikernel, something that looks fairly doable.

 *If* we indeed choose to do this I suppose that would push the Tails
 0.14 freeze date to the next Firefox ESR release date, which is October
 9th (essentially two weeks from now), so:
 
 October 9th:  0.14 freeze + release of RC1.
 October 23th: ESR backport is (hopefully) available.
 October 25th: release of RC2.
 October 30th: release of 0.14.

Fine with me.

-- 
Ague


pgpH7K9X1VIb7.pgp
Description: PGP signature
___
tails-dev mailing list
tails-dev@boum.org
https://mailman.boum.org/listinfo/tails-dev


[Tails-dev] Next release: process, schedule and iceweasel backports

2012-09-25 Thread intrigeri
Hi,

whoever is the Release Manager for the current release cycle: please
announce the freeze / RC / etc. dates ASAP. If I'm not mistaken, and
if we don't change the release schedule this time, we're supposed to
freeze in *one* week. But well, this is subject to change.

I think we're supposed to release on week 43, but... how do we deal,
next time, with an unpredictable iceweasel backports schedule?

I'm happy to focus on our APT repository for the next cycle, and it
looks like bertagaz is making great progress on the build our own
iceweasel front, but still, I'd rather not see us assume we'll be
autonomous in this area in time for the current release cycle.

So, for the current cycle, I suggest we patch our draft release
schedule from the theoretical:

/   3w\/   2w /2|5d\
major freeze  firefox
release   RC1 ESR
| |   |
| |   | RC2 release
| |   | |   |
↓ ↓   ↓ ↓   ↓
._._._._._._.
0 1 2 3 4 5 6


To the more realistic:

/   3w\/   2w /2|5d\
major freeze  ESR
release   RC1 backport is available
| |   |
| firefox |
| ESR is out  |
| |   |
| |   | RC2 release
| |   | |   |
↓ ↓   ↓ ↓   ↓
._._._._._._.
0 1 2 3 4 5 6

??

(This implies releasing two weeks later than planned, that is week 45.
Also, this assumes the backport is available two weeks after ESR is
released. Yeah, that's way too late, but we'll soon be able to
do better.)

To end with, given the amount of nice stuff we're currently merging
into devel, I'd be sad to see this wait until December before being
shipped to users, and I'm starting to wonder if we should not make the
next release a major one. That could be Tails 0.14. How crazy does
that sound?

Cheers,
-- 
  intrigeri
  | GnuPG key @ https://gaffer.ptitcanardnoir.org/intrigeri/intrigeri.asc
  | OTR fingerprint @ https://gaffer.ptitcanardnoir.org/intrigeri/otr.asc
___